Project: SpiritOfMudsuck   -  
            Listing of Entries
    (Please mouse-over any icon to get a description of that function).



Categories
  
Builder Name:Pete Dailey   -  
Project:   Sonex - Xenos-B Motorglider   -   VIEW REPORTS
Total Hours:1506.3
Total Flight Time:
Total Expense:$75148.03
Start/Last Date:Jul 01, 2016 - No Finish Date
Engine:Aerovee 2.1 Turbo
Propeller:Sensenich
Panel:MGL Avionics Explorer iEFIS/ECB/RDAC
 
Friendly URL: https://eaabuilderslog.org?s=SpiritOfMudsuck

Home or Last Project Picture

Apr 14, 2018     Rivet Port Y to Stabilator - (1.3 hours)       Category: Empennage
Used 1/8" drill to clean paint from rivet holes. Used CPP-44 for outboard (single Y) and CP-48 for inboard (double Y) rivets. None broke proud of head, though many needed two strokes to pull completely.
Was unable to properly locate bottom in board rib rivet. Will need to drill hole though Y to rib tab and rivet.


 